If 5 men can complete a work in 20 days, how many men are required to complete the same work in 10 days?

A. 10 MEN
Posted in:  Time & Work -  Aptitude -  Mathematics

A and B can complete a work in 12 days and 15 days respectively. If they work together for 3 days, how much work is left?

D. 1/3
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can complete a task in 8 hours and B can complete the same task in 12 hours, how long will it take for both A and B to complete the task if they work together?

A. 4.8 HOURS
Posted in:  Time & Work -  Aptitude -  Mathematics

A and B can complete a work in 20 days together. If A alone can complete the work in 30 days, how long will B take to complete the work alone?

A. 60 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can complete a task in 24 hours and B can complete the same task in 36 hours, how long will it take for them to finish the task together?

A. 14.4 HOURS
Posted in:  Time & Work -  Aptitude -  Mathematics