A can complete a work in 10 days, while B can complete the same work in 15 days. How many days will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can finish a piece of work in 20 days and B can finish it in 30 days, how long will it take for both A and B to finish the work together?

B. 15 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

A and B can do a piece of work in 12 days and 18 days respectively. If they work together for 6 days, how much work is left?

A. 1/3
Posted in:  Time & Work -  Aptitude -  Mathematics

A and B can complete a work in 15 days and 20 days respectively. If they work together for 5 days, how much work is left?

A. 1/3
Posted in:  Time & Work -  Aptitude -  Mathematics

C can finish a work in 20 days, while D can finish it in 30 days. If they work together, how long will it take to finish the work?

B. 15 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics