If A can complete a task in 8 hours and B can complete the same task in 12 hours, how long will it take for both A and B to complete the task if they work together?
Answer: A. 4.8 hours
The combined work rate is 1/8 + 1/12 = 5/24. Therefore, they will complete the work in 24/5 = 4.8 hours.