A and B can complete a work in 24 days and 36 days respectively. If they work together for 8 days, how much of the work is left?

A. 1/3
Posted in:  Time & Work -  Aptitude -  Mathematics

A can complete a work in 10 days, while B can complete the same work in 15 days. How long will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can do a piece of work in 20 days and B can do it in 30 days, how much work will they complete together in 5 days?

A. 1/6
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can finish a job in 24 hours and B can finish the same job in 18 hours, how long will it take for both to finish the job together?

A. 10.8 HOURS
Posted in:  Time & Work -  Aptitude -  Mathematics

If C can do a piece of work in 20 days and D can do it in 30 days, how long will it take for both C and D to complete the work together?

B. 15 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics