A can complete a work in 12 days, and B can complete the same work in 18 days. How many days will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can do a piece of work in 15 days and B can do it in 10 days, how long will it take for both A and B to complete the work together?

A. 6 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

A can complete a work in 10 days, while B can complete the same work in 15 days. How long will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can do a piece of work in 20 days and B can do it in 30 days, how much work will they complete together in 5 days?

A. 1/6
Posted in:  Time & Work -  Aptitude -  Mathematics

A can do a piece of work in 12 days, B can do it in 15 days, and C can do it in 20 days. How long will they take to complete the work together?

B. 6 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics