A can complete a work in 10 days, and B can complete the same work in 15 days. How many days will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If 5 men can complete a work in 20 days, how many days will it take for 10 men to complete the same work?

A. 10 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If a work can be completed by 8 workers in 12 days, how many workers are needed to complete the same work in 8 days?

B. 12 WORKERS
Posted in:  Time & Work -  Aptitude -  Mathematics

A and B can complete a work in 15 days and 20 days respectively. If they work together for 5 days, how much of the work is left?

A. 1/3
Posted in:  Time & Work -  Aptitude -  Mathematics

A can complete a work in 10 days, while B can complete the same work in 15 days. How many days will they take to complete the work together?

A. 6 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics