A can complete a work in 10 days and B can complete the same work in 15 days. How many days will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If 5 men can complete a work in 20 days, how many days will 10 men take to complete the same work?

A. 10 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

A can do a piece of work in 12 days and B can do it in 18 days. If they work together for 6 days, how much work is left?

C. 1/3
Posted in:  Time & Work -  Aptitude -  Mathematics

If a work can be done by 4 men in 30 days, how many men are required to complete the same work in 15 days?

B. 8 MEN
Posted in:  Time & Work -  Aptitude -  Mathematics

A cyclist covers a distance of 45 km in 1.5 hours. What is the cyclist's speed in m/s?

B. 12.5 M/S