A can complete a work in 10 days, while B can complete the same work in 15 days. How many days will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If C can complete a work in 30 days and D can complete it in 45 days, how much time will they take to finish the work together?

A. 18 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

A cyclist covers a distance of 120 kilometers in 4 hours. If he increases his speed by 10 km/h, how long will it take him to cover the same distance?

B. 3 HOURS

If a train travels at a speed of 90 km/h, how far will it travel in 3.5 hours?

A. 315 KM

If a train travels at a speed of 90 km/h, how long will it take to cover a distance of 270 kilometers?

B. 3 HOURS