If A can do a work in 24 days and B can do it in 36 days, how long will it take for A to finish the work alone after working with B for 12 days?

A. 18 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If the roots of the quadratic equation x^2 + px + q = 0 are 3 and -2, what is the value of p?

A. -1
Posted in:  Quadratic Equations -  Algebra -  Mathematics

A can complete a work in 10 days, while B can complete the same work in 15 days. How many days will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can do a piece of work in 12 days and B can do it in 18 days, how long will it take for both A and B to complete the work together?

A. 7.2 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics