A can complete a work in 12 days, while B can complete the same work in 18 days. How many days will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

If A can do a piece of work in 15 days and B can do it in 10 days, how long will it take for both A and B to complete the work together?

A. 6 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

C can finish a work in 20 days, while D can finish it in 30 days. If they work together, how long will it take them to complete the work?

B. 15 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics

A and B can complete a work in 24 days and 36 days respectively. If they work together for 8 days, how much of the work is left?

A. 1/3
Posted in:  Time & Work -  Aptitude -  Mathematics

A can complete a work in 10 days, while B can complete the same work in 15 days. How long will they take to complete the work together?

B. 8 DAYS
Posted in:  Time & Work -  Aptitude -  Mathematics