If C can complete a work in 24 days, how much work can C do in 8 days?

Answer: A. 1/3
C's work rate is 1/24 per day. In 8 days, C can complete 8*(1/24) = 1/3 of the work.
Posted in:  Time & Work -  Aptitude -  Mathematics