If a work can be done by 8 men in 12 days, how many men are required to complete the same work in 6 days?

Answer: B. 16 men
The total work is 8 * 12 = 96 man-days. To complete it in 6 days, 96/6 = 16 men are required.
Posted in:  Time & Work -  Aptitude -  Mathematics