If a work can be completed by 8 workers in 12 days, how many workers are needed to complete the same work in 8 days?

Answer: B. 12 workers
The total work is 8 workers * 12 days = 96 worker-days. To complete it in 8 days, 96/8 = 12 workers are needed.