If a work can be completed by 8 men in 12 days, how many men are required to complete the same work in 8 days?

Answer: B. 12 men
The total work is 8 men * 12 days = 96 man-days. To complete in 8 days, 96/8 = 12 men are required.
Posted in:  Time & Work -  Aptitude -  Mathematics