If A can finish a job in 24 hours and B can finish the same job in 36 hours, how long will it take for them to finish the job if they work together?

Answer: A. 14.4 hours
A's rate is 1/24 and B's rate is 1/36. Together, they work at a rate of 1/24 + 1/36 = 5/72. Therefore, they will finish the job in 72/5 = 14.4 hours.
Posted in:  Time & Work -  Aptitude -  Mathematics