If 3 men can complete a work in 10 days, how many days will it take for 5 men to complete the same work?

Answer: A. 6 days
If 3 men take 10 days, then the total work is 30 man-days. 5 men will take 30/5 = 6 days to complete the work.
Posted in:  Time & Work -  Aptitude -  Mathematics