A can do a work in 15 days and B can do it in 25 days. If they work together for 5 days, how much work is left?

Answer: A. 1/3
In 5 days, A does 1/3 of the work and B does 1/5 of the work. Together they complete 8/15 of the work, leaving 7/15.
Posted in:  Time & Work -  Aptitude -  Mathematics