A can do a work in 10 days, B in 15 days, and C in 20 days. If they all work together, how long will it take to complete the work?

Answer: B. 5 days
The combined work rate is 1/10 + 1/15 + 1/20 = 1/4. Therefore, they will complete the work in 4 days.