A can do a work in 10 days, B can do it in 15 days, and C can do it in 20 days. If they work together for 2 days, how much work is left?

Answer: B. 1/4
In 2 days, A, B, and C together complete 2 * (1/10 + 1/15 + 1/20) = 2 * (1/6) = 1/3 of the work. Thus, 1 - 1/3 = 2/3 of the work is left.