A can do a piece of work in 12 days and B can do it in 18 days. If they work together for 6 days, how much work is left?

Answer: C. 1/3
In 6 days, A and B together complete 1/2 of the work. Therefore, 1/2 of the work is left.
Posted in:  Time & Work -  Aptitude -  Mathematics