A can complete a task in 24 hours, B can complete it in 18 hours. If they work together for 6 hours, how much of the task is completed?

Answer: B. 1/3
In 6 hours, A completes 6/24 = 1/4 and B completes 6/18 = 1/3. Together, they complete 1/4 + 1/3 = 7/12 of the task.
Posted in:  Time & Work -  Aptitude -  Mathematics