A and B can do a piece of work in 15 days and 20 days respectively. If they work together for 5 days, how much work is left?

Answer: A. 1/3
In 5 days, A and B together complete 5 * (1/15 + 1/20) = 5 * (7/60) = 7/12 of the work. Thus, 1 - 7/12 = 5/12 of the work is left.