A and B can complete a work in 20 days. If A alone can complete the work in 30 days, how long will B take to complete the work alone?

Answer: C. 40 days
Let B's time to complete the work be x days. The equation is 1/30 + 1/x = 1/20. Solving gives x = 40 days.