A and B can complete a work in 15 days and 20 days respectively. If they work together for 5 days, how much of the work is completed?

Answer: A. 1/3
In 5 days, A completes 1/3 of the work and B completes 1/4, together they complete 1/3 of the work.
Posted in:  Time & Work -  Aptitude -  Mathematics