A and B can complete a work in 15 days and 20 days respectively. If they work together for 5 days, how much work is left?

Answer: A. 1/3
In 5 days, A does 1/3 of the work and B does 1/4 of the work. Together they complete 7/12 of the work, leaving 5/12.